Launch Runbook
The October platform launch, run as a checklist — the immovable anchor, the gates to clear, the countdown, and who holds what. Slippage compresses QA onto Verto hours and the two-seat team, so the gates burn down here in the open.
The anchor
The October platform launch is the fixed point the whole H2 plan swings on: Woolly Mammoth builds through launch and exits Oct 31 (notice Oct 1), then the two-seat web team plus Verto hours carry the site. Everything on this page exists to land the launch before the hand-off, with QA done on WM's watch rather than after it.
Gates to clear before launch
The countdown
September — build at full speed
- Verto specialists live Sep 1; content passes begin on the template system.
- Staging review environment carries every page before publish.
- Glossary verdicts and blog seeds move through the copy gates (Content & Copy).
- CMS bridge executed Sep 30 as Kevin exits.
October — the launch window
- WM notice Oct 1; launch-readiness QA runs on WM's watch.
- WCAG 2.1 AA remediation and Core Web Vitals pass across everything that ships.
- Redirect map live and verified by re-crawl before cutover.
- Launch, then stabilization; WM exits Oct 31 after the platform launch.
November — after the hand-off
- Launch-month testing rides Verto's bank of hours; the coding-agent workflow absorbs the capacity risk.
- The CRO agent enters shadow mode on launch-month data under the Growth backfill's ownership.
- GrowthX exits; the AI content workflow and the Digital Media & Content Specialist run content as the standing operation.
Launch-week QA checklist
- Every template audited against tokens — zero hardcoded hex, every CTA routes to Get Started.
- WCAG 2.1 AA pass and cross-browser correctness on all shipped pages.
- Tracking QA end to end: GA4 key events firing, UTM convention verified on live campaigns.
- Redirect re-crawl clean; no index junk resurfacing.
- Finalized by the launch owner before launch week. [owner to complete]
The anchor
The October platform launch is the fixed point the whole H2 plan swings on: Woolly Mammoth builds through launch and exits Oct 31 (notice Oct 1), then the two-seat web team plus Verto hours carry the site. Everything on this page exists to land the launch before the hand-off, with QA done on WM's watch rather than after it.
Gates to clear before launch
The countdown
September — build at full speed
- Verto specialists live Sep 1; content passes begin on the template system.
- Staging review environment carries every page before publish.
- Glossary verdicts and blog seeds move through the copy gates (Content & Copy).
- CMS bridge executed Sep 30 as Kevin exits.
October — the launch window
- WM notice Oct 1; launch-readiness QA runs on WM's watch.
- WCAG 2.1 AA remediation and Core Web Vitals pass across everything that ships.
- Redirect map live and verified by re-crawl before cutover.
- Launch, then stabilization; WM exits Oct 31 after the platform launch.
November — after the hand-off
- Launch-month testing rides Verto's bank of hours; the coding-agent workflow absorbs the capacity risk.
- The CRO agent enters shadow mode on launch-month data under the Growth backfill's ownership.
- GrowthX exits; the AI content workflow and the Digital Media & Content Specialist run content as the standing operation.
Launch-week QA checklist
- Every template audited against tokens — zero hardcoded hex, every CTA routes to Get Started.
- WCAG 2.1 AA pass and cross-browser correctness on all shipped pages.
- Tracking QA end to end: GA4 key events firing, UTM convention verified on live campaigns.
- Redirect re-crawl clean; no index junk resurfacing.
- Finalized by the launch owner before launch week.